Project Number: RC07-000142
Project Name: Riverwatch Pkwy. Corridor Improvements from I-20 to River Shoals
GDOT ID: 0011699
Project Description:
Construct additional turn lanes, ramp widening and traffic signal improvements on River Watch Pkwy/SR 104 from the I-20 interchange to River Shoals Drive in Augusta.
Original Budget Projections
PE |
$95,914 |
$95,914 |
ROW |
$600,000 |
$600,000 |
CST |
$1,222,896 |
$1,222,896 |
UTL |
$600,000 |
$600,000 |
Total |
$2,518,810 |
$2,518,810 |
Notes
This project would benefit the public by potentially reducing the incidence of crashes along this roadway segment, corridor, and/or intersection.
This project could potentially maximize the full utility of an existing transportation facility(s). In some cases, bypasses will be necessary. Example benefits could be: mitigating congestion (e.g. operational improvements) and optimizing capital asset management (e.g. resurfacing, rehabilitation). The impacts would apply to this roadway segment, corridor, and/or intersection.