1.1 |
Typical Trench - Water Main |
April 2019 |
January 2020
|
1.2 |
Fire Hydrant Assembly |
April 2019
|
January 2020 |
1.3 |
Vertical Gate Valve Assembly |
April 2019
|
January 2020 |
1.7 |
Tapping Valve And Sleeve |
April 2019 |
January 2020 |
1.8 |
Cut-In Gate Valve |
April 2019 |
January 2020 |
1.9 |
1" Water Service |
April 2019 |
January 2020 |
1.10 |
1.5" Inch Water Service |
April 2019 |
January 2020 |
1.11 |
2" Inch Water Service |
April 2019 |
January 2020 |
1.12 |
3" Inch Water Service |
April 2019 |
January 2020 |
1.13 |
4" Inch Water Service |
April 2019 |
January 2020 |
1.15 |
Tie-In Anchor Blocking |
April 2019
|
January 2020 |
1.16 |
Water Main Vertical Change for Crossing Conflict |
April 2019
|
January 2020 |
1.17 |
Valve Box Installation |
April 2019
|
January 2020 |
1.18 |
Valve Box Abandonment |
January 2018 |
January 2020 |
1.19 |
Water Meter Below Ground Enclosure |
January 2018 |
January 2020
|
1.20.1 |
Water Meter Vault |
April 2019
|
January 2020
|
1.20.2 |
Water Meter Above Ground Enclosure |
April 2019
|
January 2020
|
1.20.3 |
Double Detector Check Valve Assembly Fire Line Above Ground Enclosure |
January 2018 |
January 2020
|
1.20.4 |
Reduced Pressure Detector Check Valve Assembly Fire Line Above Ground Enclosure |
January 2018 |
January 2020
|
1.21.1 |
Fire Vault |
January 2018 |
January 2020
|
1.21.2 |
Fire Vault - Alt. 1 |
January 2018 |
January 2020
|
Sanitary Sewer Details |
|
2.1 |
Typical Trench - Sanitary Sewer |
April 2019
|
January 2020
|
2.2 |
Backfill Classes For Sewer Pipe Installation |
January 2018 |
January 2020
|
2.3 |
Precast Manhole |
January 2018 |
January 2020
|
2.4 |
Drop Manhole |
January 2018 |
January 2020
|
2.5 |
Doghouse Manhole |
January 2018 |
January 2020
|
2.6 |
Force Main To Gravity Manhole |
January 2018 |
January 2020
|
2.7.1 |
Manhole Frame And Cover - Onsite |
August 2018 |
January 2020
|
2.7.2 |
Manhole Frame And Cover - Offsite |
August 2018 |
January 2020
|
2.8 |
Sanitary Sewer Cleanout |
April 2019
|
January 2020
|
2.9 |
Backwater Valve |
January 2018 |
January 2020
|
2.10 |
Proposed Sewer Crossing Existing Water Main |
April 2019
|
January 2020
|
Water and Sanitary Sewer Details |
|
3.1 |
Jack And Bore (Water And Sewer Mains) |
January 2018 |
January 2020
|
3.5 |
Manhole Step |
January 2018 |
January 2020 |
Miscellaneous Details
|
|
4.1.2 |
AED Utility Road Cut Detail |
August 2018 |
January 2020 |
4 .3 |
Detector Tape |
January 2018 |
January 2020 |
4.4 |
Grease Interceptor |
January 2018 |
January 2020 |
4.5 |
Three Stage Oil / Grit Interceptor |
April 2019 |
January 2020 |
4.6 |
Typical Water & Sewer Utility Location |
January 2018 |
January 2020
|
4.7 |
Typical Lot Layout |
April 2019 |
January 2020
|
Backflow Prevention Details |
|
5.1 |
Backflow Preventer Vault |
January 2018 |
January 2020
|
5.2.1 |
Double Check Valve Assembly (2" And Smaller) |
April 2019 |
January 2020
|
5.2.2 |
Double Check Valve Assembly (2" And Smaller) |
January 2018 |
January 2020 |
5.3 |
Double Check Valve Assembly Variations (2" And Smaller) |
January 2018 |
January 2020 |
5.4 |
Double Check Valve Foundation Variations (2" And Smaller) |
January 2018 |
January 2020
|
5.5 |
Reduced Pressure Zone (RPZ) Assembly |
January 2018 |
January 2020 |
5.6 |
RPZ Above Ground Enclosure Or Double Check Assembly Properties |
January 2018 |
January 2020
|
5.7 |
Above Ground Enclosure Drain Detail |
January 2018 |
January 2020
|
5.8 |
Dual Check Assembly Installation Detail |
April 2019 |
January 2020
|