When to Call for a Mechanical Inspection

Mechanical Inspections

The following inspections should be requested according to the given rules:
  • Underground Inspection
    • After trenches or ditches are excavated
    • After the underground duct and fuel piping are installed
    • Before any backfill is put in place
  • Rough-In Inspection
    • After the roof, framing, fire blocking, and bracing are in place
    • After all ducting and other concealed components are complete
    • Before the installation of the wall or ceiling membranes
  • Mechanical Final
    • After the building is complete, the mechanical system is in place and properly connected, and the structure is ready for occupancy

Contact Information

For more information, please contact the License and Inspection Department between 8:30 am and 5:00 pm, Monday through Friday at:
  • Ph: (706) 312-5050
  • Fx: (706) 312-4277