Building Inspections
The following inspections must be requested according to the given instructions:
- Grounding
- When rebar is present in footings it shall be used as the grounding electrode. See NEC 250.52 (A)(3)
- Footing
- After excavation and reinforcing steel is in place
- Before the pouring of concrete
- When rebar is present in footings it shall be used as the grounding electrode. See NEC 250.52 (A)(3)
- Setbacks
- (stringline required on property line)
- Foundation
- After all walls and pier forms are in place
- Before any framing placed on foundation (crawl space)
- Building Slab
- After all compaction of any fill, pre-treatment, grade beams, wire mesh, and installation of vapor barrier
- Before the placement of concrete
- Framing
- After the roof, all framing, fire blocking, and bracing are in place and all concealed wiring, pipes, chimneys, ducts, and vents are complete
- Final
- After the building is complete and ready for occupancy