Mechanical & Plumbing Minimum Requirements

Mechanical

  • Underground - After fuel and refrigerant piping is installed and before backfill is placed.
  • Rough-In - After all fuel and refrigerant piping is in place, before piping is concealed, and before any fixtures or appliances are connected.
  • Final - After all piping, fixtures, and appliances are installed, connected, and tested.

Plumbing

  • Underground Piping - After piping is installed and before backfill is placed. This inspection requires a pressure test.
  • Rough-In - After soil, waste and vent, water supply, and fuel piping are in place and before piping is concealed.
  • Final - After all piping and fixtures are in place, connected, and tested.