Upgrades and Additions to the Water and Sanitary Sewer System                    
Current Projects

CIP10120 Highway 56 24in Water Main Extension Phase II

  • Design Engineer: Johnson, Laschober & Associates, P.C
  • Contractor: TBD

Project Description: Johnson
This project involves the installation of 2,000 linear feet of 24-inch diameter ductile iron pipe along Mike Padgett Highway. This second phase of the project will complete the first Phase of the proposed 24-inch Water Main system from Tobacco Road to the existing 24in WM just before Interstate - I520.

CIP10122 Highway 56 24in Water Main Extension

  • Design Engineer: Constantine Engineering
  • Contractor: TBD

Project Description: This project involves the installation of 4,000 linear feet of 24-inch diameter ductile iron pipe along Mike Padgett Highway. This project will complete the second section of the proposed 24-inch Water Main system from Interstate - I520 to Lumpkin Rd.


CIP10168 Lumpkin Road 24in Water Main Extension

  • Design Engineer: W.R.Toole Engineering
  • Contractor: TBD

Project Description: This involves the installation of 4,500 linear feet of 24-inch diameter ductile iron pipe along Lumpkin Road. This project will complete the third section of the proposed 24-inch Water Main system and start from Lumpkin Rd to Doug Barnard Parkway.

CIP10158 Road Doug Barnard Parkway 24in Water Main Extension

  • Design Engineer: W.R.Toole Engineering
  • Contractor: TBD

Project Description: This project involves the installation of 12,600 linear feet of 24-inch diameter ductile iron pipe along Doug Barnard Parkway. This project will complete the fourth section of the proposed 24-inch Water Main system and starts from Interstate - I520 to Gordon Highway.